  • Net income attributable to common stock totaled $869 million,
    $0.59 per share, in second-quarter 2018. After adjusting for net gains
    of $16 million, $0.01 per share, second-quarter 2018 adjusted net
    income attributable to common stock totaled $853 million, $0.58 per
    share.
  • Consolidated sales totaled 989 million pounds of copper, 676
    thousand ounces of gold and 24 million pounds of molybdenum in
    second-quarter 2018.
  • Consolidated sales for the year 2018 are expected to
    approximate 3.8 billion pounds of copper, 2.4 million ounces of gold
    and 95 million pounds of molybdenum, including 970 million pounds of
    copper, 700 thousand ounces of gold and 24 million pounds of
    molybdenum in third-quarter 2018.
  • Average realized prices in second-quarter 2018 were $3.08 per
    pound for copper, $1,274 per ounce for gold and $12.89 per pound for
    molybdenum.
  • Average unit net cash costs in second-quarter 2018 were $0.96
    per pound of copper and are expected to average $1.04 per pound of
    copper for the year 2018.
  • Operating cash flows totaled $1.3 billion (net of $0.2 billion
    in working capital uses and timing of other tax payments) in
    second-quarter 2018 and $2.7 billion (net of $0.2 billion in working
    capital uses and timing of other tax payments) for the first six
    months of 2018. Based on current sales volume and cost estimates, and
    assuming average prices of $2.75 per pound for copper, $1,250 per
    ounce for gold and $11.00 per pound for molybdenum for the second half
    of 2018, operating cash flows are expected to approximate $4.3 billion
    (net of $0.2 billion in working capital uses and timing of other tax
    payments) for the year 2018.
  • Capital expenditures totaled $0.5 billion (including
    approximately $0.3 billion for major mining projects) in
    second-quarter 2018 and $0.9 billion (including approximately $0.5
    billion for major mining projects) for the first six months of 2018.
    Capital expenditures for the year 2018 are expected to approximate
    $2.0 billion, including $1.1 billion for major mining projects
    primarily associated with underground development activities in the
    Grasberg minerals district in Indonesia and development of the Lone
    Star oxide project in Arizona.
  • In April 2018, FCX repaid $454 million in debt, consisting of
    the redemption of $404 million of senior notes due 2022 and $50
    million of senior notes due 2023.
  • At June 30, 2018, consolidated debt totaled $11.1 billion
    and consolidated cash totaled $3.9 billion. FCX had no
    borrowings and $3.5 billion available under its revolving credit
    facility at June 30, 2018.
  • On June 27, 2018, FCX declared a quarterly cash dividend
    of $0.05 per share on its common stock, which will be paid on August
    1, 2018.
  • In July 2018, FCX and PT Freeport Indonesia (PT-FI) entered into a non-binding
    Heads of Agreement
    with PT Indonesia Asahan Aluminium (Persero)
    (Inalum) and Rio Tinto to establish a new long-term partnership
    between FCX, Inalum and the Indonesian government.

Freeport-McMoRan Inc. (NYSE:FCX) reported net income attributable to
common stock of $869 million ($0.59 per share) in second-quarter 2018
and $1.6 billion ($1.07 per share) for the first six months of 2018,
compared with $268 million ($0.18 per share) in second-quarter 2017 and
$496 million ($0.34 per share) for the first six months of 2017. After
adjusting for net gains of $16 million ($0.01 per share), adjusted net
income attributable to common stock totaled $853 million ($0.58 per
share) in second-quarter 2018. Refer to the supplemental schedule,
"Adjusted Net Income," on page VII, which is available on FCX's website,
"fcx.com," for additional information.

Richard C. Adkerson, President and Chief Executive Officer, said,
"Our second quarter results reflect strong performance from our global
operations and a continued focus on productivity, cost management and
capital discipline. During the first half of 2018, we generated $2.7
billion in cash flow from operations and capital expenditures totaled
$0.9 billion, enabling further strengthening of our balance sheet and
advancement of initiatives to build value for FCX shareholders. We
achieved important progress during the quarter to reach a new long-term
partnership structure with the Indonesian government, and we remain
focused on completing negotiation and documentation of definitive
agreements to restore long-term stability for our Grasberg operations.

Despite the recent decline in copper prices associated with the
uncertain impact on the global economy of recent international trade
actions, we remain positive on the outlook for copper prices given
limitations on supply and the important role of copper in the global
economy. To date, we have not experienced a decline in demand for our
products, but will be prepared to adjust our plans if necessary to
respond to market conditions. Our shareholders are well positioned to
benefit from FCX's global leadership position in copper, supported by a
large, high-quality portfolio of long-lived, geographically diverse
assets."

SUMMARY FINANCIAL DATA

   
Three Months Ended Six Months Ended
June 30, June 30,
2018   2017 2018   2017
(in millions, except per share amounts)

Revenuesa,b

$ 5,168 $ 3,711 $ 10,036 $ 7,052
Operating incomea $ 1,664 $ 686 $ 3,123 $ 1,283
Net income from continuing operations $ 1,039 $ 326 $ 1,867 $ 594
Net (loss) income from discontinued operationsc $ (4 ) $ 9 $ (15 ) $ 47
Net income attributable to common stockd,e $ 869 $ 268 $ 1,561 $ 496
Diluted net income (loss) per share of common stock:
Continuing operations $ 0.59 $ 0.18 $ 1.08 $ 0.31
Discontinued operations     (0.01 ) 0.03
$ 0.59   $ 0.18   $ 1.07   $ 0.34
Diluted weighted-average common shares outstanding 1,458 1,453 1,458 1,453
Operating cash flowsf $ 1,309 $ 1,037 $ 2,678 $ 1,829
Capital expenditures $ 482 $ 362 $ 884 $ 706
At June 30:
Cash and cash equivalents $ 3,859 $ 4,667 $ 3,859 $ 4,667
Total debt, including current portion $ 11,127 $ 15,354 $ 11,127 $ 15,354
 

a.

 

For segment financial results, refer to the supplemental
schedules, "Business Segments," beginning on page IX, which are
available on FCX's website, "fcx.com."

b.

Includes adjustments to prior period provisionally priced
concentrate and cathode copper sales totaling $23 million ($9
million to net income attributable to common stock or $0.01 per
share) in second-quarter 2018, $(20) million ($(8) million to net
income attributable to common stock or $(0.01) per share) in
second-quarter 2017, $(70) million ($(31) million to net income
attributable to common stock or $(0.02) per share) for the first
six months of 2018 and $81 million ($35 million to net income
attributable to common stock or $0.02 per share) for the first six
months of 2017. For further discussion, refer to the supplemental
schedule, "Derivative Instruments," beginning on page VIII, which
is available on FCX's website, "fcx.com."

c.

Primarily reflects adjustments to the fair value of contingent
consideration related to the 2016 sale of FCX's interest in TF
Holdings Limited, which will continue to be adjusted through
December 31, 2019.

d.

Includes net gains of $16 million ($0.01 per share) in
second-quarter 2018, $27 million ($0.01 per share) in
second-quarter 2017, $27 million ($0.02 per share) for the first
six months of 2018 and $34 million ($0.02 per share) for the first
six months of 2017 that are described in the supplemental
schedule, "Adjusted Net Income," on page VII, which is available
on FCX's website, "fcx.com."

e.

FCX defers recognizing profits on intercompany sales until
final sales to third parties occur. For a summary of net impacts
from changes in these deferrals, refer to the supplemental
schedule, "Deferred Profits," on page IX, which is available on
FCX's website, "fcx.com."

f.

Includes net working capital (uses) sources and timing of other
tax payments of $(192) million in second-quarter 2018, $154
million in second-quarter 2017, $(213) million for the first six
months of 2018 and $343 million for the first six months of 2017.

 

SUMMARY OPERATING DATA

   

Three Months Ended

Six Months Ended

June 30,

June 30,
2018   2017 2018   2017
Copper (millions of recoverable pounds)
Production 1,014 883 1,966 1,734
Sales, excluding purchases 989 942 1,982 1,751
Average realized price per pound $ 3.08 $ 2.65 $ 3.10 $ 2.65
Site production and delivery costs per pounda $ 1.69 $ 1.63 $ 1.68 $ 1.61
Unit net cash costs per pounda $ 0.96 $ 1.19 $ 0.97 $ 1.28
Gold (thousands of recoverable ounces)
Production 746 353 1,345 592
Sales, excluding purchases 676 432 1,286 614
Average realized price per ounce $ 1,274 $ 1,243 $ 1,291 $ 1,242
Molybdenum (millions of recoverable pounds)
Production 24 23 46 46
Sales, excluding purchases 24 25 48 49
Average realized price per pound $ 12.89 $ 9.58 $ 12.42 $ 9.16
 

a.

 

Reflects per pound weighted-average production and delivery
costs and unit net cash costs (net of by-product credits) for all
copper mines, before net noncash and other costs. For
reconciliations of per pound unit costs by operating division to
production and delivery costs applicable to sales reported in
FCX's consolidated financial statements, refer to the supplemental
schedules, "Product Revenues and Production Costs," beginning on
page XII, which are available on FCX's website, "fcx.com."

 

Consolidated Sales Volumes

Second-quarter 2018 copper sales of 989 million pounds were
higher than the April 2018 estimate of 970 million pounds and higher
than second-quarter 2017 sales of 942 million pounds, primarily
reflecting higher mining and milling rates and higher ore grades in
Indonesia.

Second-quarter 2018 gold sales of 676 thousand ounces were lower
than the April 2018 estimate of 700 thousand ounces, primarily because
of timing of shipments, and were higher than second-quarter 2017 sales
of 432 thousand ounces, primarily reflecting higher ore grades and
operating rates in Indonesia. Lower second-quarter 2017 operating rates
in Indonesia included the impact of labor disruptions at PT-FI in the
first half of 2017.

Second-quarter 2018 molybdenum sales of 24 million pounds
approximated the April 2018 estimate of 24 million pounds and
second-quarter 2017 sales of 25 million pounds.

Sales volumes for the year 2018 are expected to approximate 3.8 billion
pounds of copper, 2.4 million ounces of gold and 95 million pounds of
molybdenum, including 970 million pounds of copper, 700 thousand ounces
of gold and 24 million pounds of molybdenum in third-quarter 2018.

Projections for 2018 and other forward looking statements in this
release assume resolution of PT-FI's long-term mining rights or an
extension of PT-FI's temporary special mining license (IUPK) after July
31, 2018. Refer to "Indonesia Mining," beginning on page 7, for further
discussion of Indonesia regulatory matters which could have a
significant impact on future results.

Consolidated Unit Costs

Consolidated average unit net cash costs (net of by-product credits) for
FCX's copper mines of $0.96 per pound of copper in second-quarter 2018
were lower than unit net cash costs of $1.19 per pound in second-quarter
2017, primarily reflecting higher by-product credits.

Assuming average prices of $1,250 per ounce of gold and $11.00 per pound
of molybdenum for the second half of 2018 and achievement of current
sales volume and cost estimates, consolidated unit net cash costs (net
of by-product credits) for copper mines are expected to average $1.04
per pound of copper for the year 2018. The impact of price changes on
consolidated unit net cash costs would approximate $0.015 per pound for
each $50 per ounce change in the average price of gold and $0.02 per
pound for each $2 per pound change in the average price of molybdenum
for the second half of 2018. Quarterly unit net cash costs vary with
fluctuations in sales volumes and realized prices, primarily for gold
and molybdenum.

MINING OPERATIONS

North America Copper Mines. FCX operates seven open-pit copper
mines in North America - Morenci, Bagdad, Safford, Sierrita and Miami in
Arizona, and Chino and Tyrone in New Mexico. In addition to copper,
certain of FCX's North America copper mines produce molybdenum
concentrate, gold and silver.

All of the North America mining operations are wholly owned, except for
Morenci. FCX records its 72 percent undivided joint venture interest in
Morenci using the proportionate consolidation method.

Operating and Development Activities. FCX has significant
undeveloped reserves and resources in North America and a portfolio of
potential long-term development projects. Future investments will be
undertaken based on the results of economic and technical feasibility
studies, and are dependent on market conditions. FCX continues to study
opportunities to reduce the capital intensity of its potential long-term
development projects.

Through exploration drilling, FCX has identified a significant resource
at its wholly owned Lone Star project located near the Safford operation
in eastern Arizona. An initial project to develop the Lone Star oxide
ores has commenced with first production expected by the end of 2020.
Total capital costs, including mine equipment and pre-production
stripping, are expected to approximate $850 million and will benefit
from the utilization of existing infrastructure at the adjacent Safford
operation. As of June 30, 2018, $113 million has been incurred for this
project. Production from the Lone Star oxide ores is expected to average
approximately 200 million pounds of copper per year with an approximate
20-year mine life. The project also advances the potential for
development of a larger-scale district opportunity. FCX is conducting
additional drilling following positive exploration results and continues
to evaluate longer term opportunities available from the significant
long-term sulfide potential in the Lone Star/Safford minerals district.

Operating Data. Following is summary consolidated operating data
for the North America copper mines for the second quarters and first six
months of 2018 and 2017:

   
Three Months Ended Six Months Ended
June 30, June 30,
2018   2017 2018   2017
Copper (millions of recoverable pounds)
Production 354 384 702 776
Sales, excluding purchases 361 408 745 783
Average realized price per pound $ 3.12 $ 2.62 $ 3.14 $ 2.65
 
Molybdenum (millions of recoverable pounds)
Productiona 8 8 15 17
 
Unit net cash costs per pound of copperb
Site production and delivery, excluding adjustments $ 1.94 $ 1.58 $ 1.89 $ 1.54
By-product credits (0.25 ) (0.16 ) (0.22 ) (0.15 )
Treatment charges 0.10   0.10   0.10   0.10  
Unit net cash costs $ 1.79   $ 1.52   $ 1.77   $ 1.49  
 

a.

 

Refer to summary operating data on page 3 for FCX's
consolidated molybdenum sales, which includes sales of molybdenum
produced at the North America copper mines.

b.

For a reconciliation of unit net cash costs per pound to
production and delivery costs applicable to sales reported in
FCX's consolidated financial statements, refer to the supplemental
schedules, "Product Revenues and Production Costs," beginning on
page XII, which are available on FCX's website, "fcx.com."

 

North America's consolidated copper sales volumes of 361 million pounds
in second-quarter 2018 were lower than second-quarter 2017 sales of 408
million pounds, primarily reflecting anticipated lower ore grades and
timing of second-quarter 2017 shipments. North America copper sales are
estimated to approximate 1.45 billion pounds for the year 2018, compared
with 1.5 billion pounds in 2017.

Average unit net cash costs (net of by-product credits) for the North
America copper mines of $1.79 per pound of copper in second-quarter 2018
were higher than unit net cash costs of $1.52 per pound in
second-quarter 2017, primarily reflecting lower sales volumes and higher
mining and milling costs, partly offset by higher by-product credits.

Average unit net cash costs (net of by-product credits) for the North
America copper mines are expected to approximate $1.78 per pound of
copper for the year 2018, based on achievement of current sales volume
and cost estimates and assuming an average molybdenum price of $11.00
per pound for the second half of 2018. North America's average unit net
cash costs for the year 2018 would change by approximately $0.02 per
pound for each $2 per pound change in the average price of molybdenum
for the second half of 2018.

South America Mining. FCX operates two copper mines in South
America - Cerro Verde in Peru (in which FCX owns a 53.56 percent
interest) and El Abra in Chile (in which FCX owns a 51 percent
interest). These operations are consolidated in FCX's financial
statements. In addition to copper, the Cerro Verde mine produces
molybdenum concentrate and silver.

Operating and Development Activities. Cerro Verde's expanded
operations benefit from its large-scale, long-lived reserves and cost
efficiencies. The Cerro Verde expansion project, which achieved capacity
operating rates in early 2016, expanded the concentrator facilities'
capacity from 120,000 metric tons of ore per day to 360,000 metric tons
of ore per day. In March 2018, Cerro Verde received a modified
environmental permit allowing it to operate its existing concentrator
facilities at rates up to 409,500 metric tons of ore per day. Cerro
Verde's concentrator facilities have continued to perform well, with
average mill throughput rates of 385,300 metric tons of ore per day for
the first six months of 2018.

Exploration results at El Abra indicate a significant sulfide resource,
which could potentially support a major mill project similar to
facilities constructed at Cerro Verde. FCX continues to evaluate a
large-scale expansion at El Abra to process additional sulfide material
and to achieve higher recoveries. Future investments will depend on
technical studies, which are being advanced, economic factors and market
conditions.

Operating Data. Following is summary consolidated operating data
for the South America mining operations for the second quarters and
first six months of 2018 and 2017:

   
Three Months Ended Six Months Ended
June 30, June 30,
2018   2017 2018   2017
Copper (millions of recoverable pounds)
Production 313 300 606 604
Sales 312 287 602 596
Average realized price per pound $ 3.07 $ 2.67 $ 3.09 $ 2.65
 
Molybdenum (millions of recoverable pounds)
Productiona 7 7 13 13
 
Unit net cash costs per pound of copperb
Site production and delivery, excluding adjustments $ 1.77 $ 1.55 $ 1.78 $ 1.52
By-product credits (0.22 ) (0.13 ) (0.24 ) (0.16 )
Treatment charges 0.18 0.22 0.19 0.22
Royalty on metals 0.01   0.01   0.01   0.01  
Unit net cash costs $ 1.74   $ 1.65   $ 1.74   $ 1.59  
 

a.

 

Refer to summary operating data on page 3 for FCX's
consolidated molybdenum sales, which includes sales of molybdenum
produced at Cerro Verde.

b.

For a reconciliation of unit net cash costs per pound to
production and delivery costs applicable to sales reported in
FCX's consolidated financial statements, refer to the supplemental
schedules, "Product Revenues and Production Costs," beginning on
page XII, which are available on FCX's website, "fcx.com."

 

South America's consolidated copper sales volumes of 312 million pounds
in second-quarter 2018 were higher than second-quarter 2017 sales of 287
million pounds, primarily reflecting higher mining and milling rates and
timing of second-quarter 2017 shipments, partly offset by lower ore
grades. Sales from South America mining are expected to approximate 1.2
billion pounds of copper for the year 2018, compared with 1.2 billion
pounds of copper in 2017.

Average unit net cash costs (net of by-product credits) for South
America mining of $1.74 per pound of copper in second-quarter 2018 were
higher than unit net cash costs of $1.65 per pound in second-quarter
2017, primarily reflecting higher mining and input costs, partly offset
by higher volumes and by-product credits. Average unit net cash costs
(net of by-product credits) for South America mining are expected to
approximate $1.67 per pound of copper for the year 2018, based on
current sales volume and cost estimates and assuming an average price of
$11.00 per pound of molybdenum for the second half of 2018.

Cerro Verde and its workers' union are negotiating a new collective
labor agreement to replace the agreement that expires August 31, 2018.

Indonesia Mining. Through its 90.64 percent owned and
consolidated subsidiary PT-FI, FCX's assets include one of the world's
largest copper and gold deposits at the Grasberg minerals district in
Papua, Indonesia. PT-FI operates a proportionately consolidated joint
venture, which produces copper concentrate that contains significant
quantities of gold and silver.

Regulatory Matters. PT-FI continues to actively engage with
Indonesian government officials to address regulatory changes that
conflict with its contractual rights in a manner that provides long-term
stability for PT-FI's operations and investment plans, and protects
value for FCX's shareholders.

The parties have been engaged in negotiation and documentation of an
IUPK and accompanying documentation for assurances on legal and fiscal
terms to provide PT-FI with long-term mining rights through 2041. In
addition, the IUPK would provide that PT-FI construct a smelter within
five years of reaching a definitive agreement and include agreement for
the divestment of 51 percent of the project area interests to Indonesian
participants at fair market value.

In July 2018, FCX entered into a Heads of Agreement with the Indonesian
state-owned enterprise Inalum and PT-FI's joint venture partner Rio
Tinto. Under the terms of the non-binding agreement, Inalum would
acquire for aggregate cash consideration of $3.85 billion all of Rio
Tinto's interests associated with its joint venture with PT-FI (Joint
Venture) and FCX's interests in PT Indocopper Investama, which owns 9.36
percent of PT-FI.

Inalum would contribute the Rio Tinto interests to PT-FI, which would
expand PT-FI's asset base, in exchange for a 40 percent share ownership
in PT-FI, pursuant to arrangements that would enable FCX and existing
PT-FI shareholders to retain the economics of the revenue and cost
sharing arrangements under the Joint Venture. Following completion of
the transaction, Inalum's share ownership would approximate 51 percent
of PT-FI (subject to an agreement between shareholders to replicate the
Joint Venture economics) and FCX's ownership would approximate 49
percent.

At closing, Rio Tinto would receive $3.5 billion and FCX would receive
$350 million in cash proceeds from Inalum. In addition, Rio Tinto would
forego in favor of FCX an amount equivalent to Rio Tinto's share of
Joint Venture cash flows since January 1, 2018, through closing.

Following completion of the ownership restructuring, FCX does not expect
its economic exposure to PT-FI to change significantly. FCX expects its
share of future cash flows of the expanded PT-FI asset base, combined
with the cash proceeds received in the transaction, to be comparable to
its existing share of future cash flows under the current Joint Venture
arrangement. FCX would also continue to manage the operations of PT-FI.

The transaction, which is expected to close during the second half of
2018, is subject to the negotiation and documentation of definitive
agreements, including purchase and sale agreements, the extension and
stability of PT-FI's long-term mining rights through 2041 in a form
acceptable to FCX and Inalum, a shareholders' agreement between FCX and
Inalum providing for continuity of FCX's management of PT-FI's
operations and addressing governance arrangements, and resolution of
environmental regulatory matters pending before Indonesia's Ministry of
Environment and Forestry satisfactory to the Indonesian government, FCX
and Inalum. The terms of these agreements will be subject to approval by
the FCX Board of Directors (Board).

In February 2018, PT-FI's export license was extended to February 15,
2019, and in July 2018, PT-FI's temporary IUPK was extended to July 31,
2018. PT-FI is seeking an extension of the temporary IUPK to remain in
effect until definitive agreements are complete. Until definitive
agreements are reached, PT-FI has reserved all rights under its Contract
of Work (COW), including pursuing arbitration under the dispute
resolution procedures.

Operating and Development Activities. PT-FI is currently mining
the final phase of the Grasberg open pit, which contains high copper and
gold ore grades. PT-FI has revised its mine plans to extend mining
activities in the open pit by approximately six months following results
of an economic analysis. PT-FI expects to mine ore from the open pit
until transitioning to the Grasberg Block Cave underground mine in the
first half of 2019. Lower copper and gold production from Indonesia
mining is expected during the transition period in 2019 and 2020.

PT-FI has several projects in the Grasberg minerals district related to
the development of its large-scale, long-lived, high-grade underground
ore bodies. In aggregate, these underground ore bodies are expected to
produce large-scale quantities of copper and gold following the
transition from the Grasberg open pit. Substantial progress has been
made to prepare for the transition to mining of the Grasberg Block Cave
underground mine. Mine development activities are sufficiently advanced
to commence caving in the first half of 2019. The ore flow and
underground rail haulage systems are expected to be fully commissioned
and operational in the second half of 2018.

PT-FI has revised its mine plan for the ramp-up of the Deep Mill Level
Zone (DMLZ) underground mine following mining-induced seismic activity
that began in 2017 and continued during 2018. During second-quarter
2018, PT-FI initiated plans to conduct hydraulic fracturing activities
to manage rock stresses and pre-condition the DMLZ for large-scale
production. PT-FI's revised mine plans, which will continue to be
reviewed, currently project block cave mining activities in the DMLZ to
commence in mid-2019 following a period of hydraulic fracturing
activities designed to safely manage production. PT-FI continues to
expect the DMLZ to reach full production rates of 80,000 metric tons per
day in 2022.

Subject to reaching a definitive agreement with the Indonesian
government on PT-FI's long-term mining rights, estimated annual capital
spending on these projects would average $0.8 billion per year ($0.7
billion per year net to PT-FI) over the next five years. Considering the
long-term nature and size of these projects, actual costs could vary
from these estimates. In response to market conditions and Indonesian
regulatory uncertainty, the timing of these expenditures continues to be
reviewed and could be reduced or deferred significantly.

Operating Data. Following is summary consolidated operating data
for the Indonesia mining operations for the second quarters and first
six months of 2018 and 2017:

 
Three Months Ended Six Months Ended
June 30, June 30,
2018   2017 2018   2017
Copper (millions of recoverable pounds)
Production 347 199 658 354
Sales 316 247 635 372
Average realized price per pound $ 3.05 $ 2.67 $ 3.07 $ 2.64
 
Gold (thousands of recoverable ounces)
Production 740 348 1,335 580
Sales 671 427 1,274 604
Average realized price per ounce $ 1,274 $ 1,243 $ 1,291 $ 1,242
 
Unit net cash (credits) costs per pound of coppera
Site production and delivery, excluding adjustments $ 1.33 $ 1.77 b $ 1.34 $ 1.89

b

Gold and silver credits (2.76 ) (2.21 ) (2.67 ) (2.10 )
Treatment charges 0.26 0.26 0.25 0.27
Export duties 0.18 0.11 0.16 0.11
Royalty on metals 0.22   0.17   0.22   0.17  
Unit net cash (credits) costs $ (0.77 ) $ 0.10   $ (0.70 ) $ 0.34  
 

a.

 

For a reconciliation of unit net cash (credits) costs per pound
to production and delivery costs applicable to sales reported in
FCX's consolidated financial statements, refer to the supplemental
schedules, "Product Revenues and Production Costs," beginning on
page XII, which are available on FCX's website, "fcx.com."

b.

Excludes fixed costs charged directly to production and
delivery costs totaling $82 million ($0.33 per pound of copper) in
second-quarter 2017 and $103 million ($0.28 per pound of copper)
for the first six months of 2017 associated with workforce
reductions.

 

Indonesia's consolidated sales of 316 million pounds of copper and 671
thousand ounces of gold in second-quarter 2018 were higher than
second-quarter 2017 sales of 247 million pounds of copper and 427
thousand ounces of gold, primarily reflecting higher operating rates and
ore grades. Lower second-quarter 2017 operating rates included the
impact of labor disruptions in the first half of 2017.

Assuming achievement of planned operating rates for the second half of
2018, consolidated sales volumes from Indonesia mining are expected to
approximate 1.15 billion pounds of copper and 2.4 million ounces of gold
for the year 2018, compared with 1.0 billion pounds of copper and 1.5
million ounces of gold for the year 2017. Because of the transition to
underground mining, PT-FI's production is expected to be significantly
lower in 2019 and 2020, compared to 2018.

A significant portion of PT-FI's costs are fixed and unit costs vary
depending on production volumes and other factors. As a result of higher
sales volumes and gold and silver credits, Indonesia had unit net cash
credits (including gold and silver credits) of $0.77 per pound of copper
in second-quarter 2018, compared with unit net cash costs of $0.10 per
pound in second-quarter 2017.

Assuming an average gold price of $1,250 per ounce for the second half
of 2018 and achievement of current sales volume and cost estimates, unit
net cash credits (including gold and silver credits) for Indonesia
mining are expected to approximate $0.58 per pound of copper for the
year 2018. Indonesia mining's unit net cash credits for the year 2018
would change by approximately $0.06 per pound for each $50 per ounce
change in the average price of gold for the second half of 2018. Because
of the fixed nature of a large portion of Indonesia's costs, unit net
cash credits/costs vary from quarter to quarter depending on copper and
gold volumes.

Indonesia mining's projected sales volumes and unit net cash credits for
the year 2018 are dependent on a number of factors, including
operational performance, workforce productivity, timing of shipments,
and Indonesia regulatory matters, including the resolution of PT-FI's
long-term mining rights or an extension of PT-FI's temporary IUPK after
July 31, 2018.

Molybdenum Mines. FCX has two wholly owned molybdenum mines - the
Henderson underground mine and the Climax open-pit mine - both in
Colorado. The Henderson and Climax mines produce high-purity,
chemical-grade molybdenum concentrate, which is typically further
processed into value-added molybdenum chemical products. The majority of
molybdenum concentrate produced at the Henderson and Climax mines, as
well as from FCX's North America and South America copper mines, is
processed at FCX's conversion facilities.

Operating and Development Activities. Production from the
Molybdenum mines totaled 9 million pounds of molybdenum in
second-quarter 2018 and 8 million pounds in second-quarter 2017. Refer
to summary operating data on page 3 for FCX's consolidated molybdenum
sales and average realized prices, which includes sales of molybdenum
produced at the Molybdenum mines, and from FCX's North America and South
America copper mines.

Unit net cash costs for the Molybdenum mines averaged $8.36 per pound of
molybdenum in second-quarter 2018 and $7.73 per pound in second-quarter
2017. Based on current sales volume and cost estimates, average unit net
cash costs for the Molybdenum mines are expected to approximate $8.75
per pound of molybdenum for the year 2018.

For a reconciliation of unit net cash costs per pound to production and
delivery costs applicable to sales reported in FCX's consolidated
financial statements, refer to the supplemental schedules, "Product
Revenues and Production Costs," beginning on page XII, which are
available on FCX's website, "fcx.com."

Mining Exploration Activities. FCX's mining exploration
activities are generally associated with its existing mines, focusing on
opportunities to expand reserves and resources to support development of
additional future production capacity. A drilling program to further
delineate the Lone Star resource continues to indicate additional
mineralization in this district. Exploration results continue to
indicate opportunities for significant future potential reserve
additions in North America and South America. Exploration spending is
expected to approximate $90 million for the year 2018.

CASH FLOWS, CASH and DEBT

Operating Cash Flows. FCX generated operating cash flows of $1.3
billion (net of $0.2 billion in working capital uses and timing of other
tax payments) in second-quarter 2018 and $2.7 billion (net of $0.2
billion in working capital uses and timing of other tax payments) for
the first six months of 2018.

Based on current sales volume and cost estimates, and assuming average
prices of $2.75 per pound of copper, $1,250 per ounce of gold and $11.00
per pound of molybdenum for the second half of 2018, FCX's consolidated
operating cash flows are estimated to approximate $4.3 billion for the
year 2018 (net of $0.2 billion in working capital uses and timing of
other tax payments). The impact of price changes during the second half
of 2018 on operating cash flows would approximate $185 million for each
$0.10 per pound change in the average price of copper, $60 million for
each $50 per ounce change in the average price of gold and $55 million
for each $2 per pound change in the average price of molybdenum.

Capital Expenditures. Capital expenditures totaled $0.5 billion
in second-quarter 2018 (including approximately $0.3 billion for major
mining projects) and $0.9 billion for the first six months of 2018
(including approximately $0.5 billion for major mining projects).
Capital expenditures are expected to approximate $2.0 billion for the
year 2018, including $1.1 billion for major mining projects primarily
associated with underground development activities in the Grasberg
minerals district and development of the Lone Star oxide project.

Cash. Following is a summary of the U.S. and international
components of consolidated cash and cash equivalents available to the
parent company, net of noncontrolling interests' share, taxes and other
costs at June 30, 2018 (in billions):

 
Cash at domestic companies $ 2.9
Cash at international operations 1.0  
Total consolidated cash and cash equivalents 3.9
Noncontrolling interests' share (0.4 )
Cash, net of noncontrolling interests' share 3.5
Withholding taxes and other (0.1 )
Net cash available $ 3.4  
 

Debt. Following is a summary of total debt and the related
weighted-average interest rates at June 30, 2018 (in billions, except
percentages):

   
Weighted-
Average
Interest Rate
Senior Notes $ 9.9 4.6%
Cerro Verde credit facility 1.2   4.0%
Total debt $ 11.1   4.5%
 

In April 2018, FCX redeemed $404 million of senior notes due 2022 and
$50 million of senior notes due 2023, resulting in aggregate annual cash
interest savings of approximately $30 million. In second-quarter 2018,
FCX recorded a net gain on early extinguishment of debt totaling $9
million primarily related to these redemptions.

During April 2018, FCX entered into a new $3.5 billion, five-year,
unsecured revolving credit facility with substantially similar structure
and terms as its prior facility, which was scheduled to mature in May
2019. At June 30, 2018, FCX had no borrowings, $13 million in letters of
credit issued and $3.5 billion available under its revolving credit
facility.

FINANCIAL POLICY

In February 2018, the Board reinstated a cash dividend on FCX common
stock. On June 27, 2018, FCX declared a quarterly cash dividend of $0.05
per share on its common stock, which will be paid on August 1, 2018, to
shareholders of record as of July 13, 2018. The declaration of dividends
is at the discretion of the Board and will depend upon FCX's financial
results, cash requirements, future prospects and other factors deemed
relevant by the Board.

WEBCAST INFORMATION

A conference call with securities analysts to discuss FCX's
second-quarter 2018 results is scheduled for today at 10:00 a.m. Eastern
Time. The conference call will be broadcast on the Internet along with
slides. Interested parties may listen to the conference call live and
view the slides by accessing "fcx.com." A replay of the webcast will be
available through Friday, August 24, 2018.

-----------------------------------------------------------------------------------------------------------

FCX is a leading international mining company with headquarters in
Phoenix, Arizona. FCX operates large, long-lived, geographically diverse
assets with significant proven and probable reserves of copper, gold and
molybdenum. FCX is the world's largest publicly traded copper producer.
FCX's portfolio of assets includes the Grasberg minerals district in
Indonesia, one of the world's largest copper and gold deposits; and
significant mining operations in the Americas, including the large-scale
Morenci minerals district in North America and the Cerro Verde operation
in South America. Additional information about FCX is available on FCX's
website at "fcx.com."

Cautionary Statement and Regulation G Disclosure: This press
release contains forward-looking statements in which FCX discusses its
potential future performance. Forward-looking statements are all
statements other than statements of historical facts, such as
projections or expectations relating to ore grades and milling rates,
production and sales volumes, unit net cash costs, operating cash flows,
capital expenditures, the transaction contemplated by the non-binding
Heads of Agreement between FCX, PT-FI, Inalum and Rio Tinto, exploration
efforts and results, development and production activities and costs,
liquidity, tax rates, the impact of copper, gold and molybdenum price
changes, the impact of deferred intercompany profits on earnings,
reserve estimates, future dividend payments, and share purchases and
sales. The words "anticipates," "may," "can," "plans," "believes,"
"estimates," "expects," "projects," "targets," "intends," "likely,"
"will," "should," "to be," "potential" and any similar expressions are
intended to identify those assertions as forward-looking statements. The
declaration of dividends is at the discretion of the Board and will
depend on FCX's financial results, cash requirements, future prospects,
and other factors deemed relevant by the Board.

FCX cautions readers that forward-looking statements are not
guarantees of future performance and actual results may differ
materially from those anticipated, projected or assumed in the
forward-looking statements. Important factors that can cause FCX's
actual results to differ materially from those anticipated in the
forward-looking statements include supply of and demand for, and prices
of, copper, gold and
molybdenum; mine sequencing; production
rates; potential inventory adjustments; potential impairment of
long-lived mining assets; FCX's ability to complete the transaction
contemplated by the non-binding Heads of Agreement, which is subject to
the negotiation and documentation of definitive agreements, including
purchase and sale agreements, the extension and stability of PT-FI's
long-term mining rights through 2041 in a form acceptable to FCX and
Inalum, a shareholders' agreement between FCX and Inalum providing for
continuity of FCX's management of PT-FI's operations and addressing
governance arrangements, and resolution of administrative sanctions and
environmental regulatory matters pending before Indonesia's Ministry of
Environment and Forestry satisfactory to the Indonesian government, FCX
and Inalum, the terms of all of which will be subject to FCX Board
approval; PT-FI's ability to obtain an extension of its temporary IUPK
after July 31, 2018; the potential effects of violence in Indonesia
generally and in the province of Papua; industry risks; regulatory
changes; political risks; labor relations; weather- and climate-related
risks; environmental risks (including resolution of the administrative
sanctions and other environmental matters pending before Indonesia's
Ministry of Environment and Forestry); litigation results (including the
final disposition of Indonesian tax disputes and the outcome of Cerro
Verde's royalty dispute with the Peruvian national tax authority); and
other factors described in more detail under the heading "Risk Factors"
in FCX's Annual Report on Form 10-K for the year ended December 31,
2017, filed with the U.S. Securities and Exchange Commission (SEC) as
updated by FCX's subsequent filings with the SEC.

Investors are cautioned that many of the assumptions upon which FCX's
forward-looking statements are based are likely to change after the
forward-looking statements are made, including for example commodity
prices, which FCX cannot control, and production volumes and costs, some
aspects of which FCX may not be able to control. Further, FCX may make
changes to its business plans that could affect its results. FCX
cautions investors that it does not intend to update forward-looking
statements more frequently than quarterly notwithstanding any changes in
its assumptions, changes in business plans, actual experience or other
changes, and FCX undertakes no obligation to update any forward-looking
statements.

This press release also contains certain financial measures such as
unit net cash (credits) costs per pound of copper and molybdenum and
adjusted net income, which are not recognized under U.S. generally
accepted accounting principles. As required by SEC Regulation G,
reconciliations of these measures to amounts reported in FCX's
consolidated financial statements are in the supplemental schedules of
this press release, which are also available on FCX's website, "fcx.com."

 
FREEPORT-McMoRan INC.
SELECTED OPERATING DATA
     
Three Months Ended June 30,
2018 2017 2018 2017
MINING OPERATIONS: Production Sales

COPPER (millions of
recoverable pounds)

(FCX's net interest in %)

North America

Morenci (72%)a 182 187 183 196
Bagdad (100%) 48 43 48 43
Safford (100%) 29 37 32 42
Sierrita (100%) 36 40 38 42
Miami (100%) 4 5 4 5
Chino (100%) 42 58 43 63
Tyrone (100%) 13 14 13 17
Other (100%)        
Total North America 354   384   361   408  
 

South America

Cerro Verde (53.56%) 262 260 258 244
El Abra (51%) 51   40   54   43  
Total South America 313   300   312   287  
 

Indonesia

Grasberg (90.64%)b 347   199   316   247  
Total 1,014 883 989 c 942 c
Less noncontrolling interests 179   159   176   158  
Net 835   724   813   784  
 
Average realized price per pound $ 3.08 $ 2.65
 

GOLD (thousands of recoverable
ounces)

(FCX's net interest in %)
North America (100%) 6 5 5 5
Indonesia (90.64%)b 740   348   671   427  
Consolidated 746 353 676 432
Less noncontrolling interests 70   32   63   40  
Net 676   321   613   392  
 
Average realized price per ounce $ 1,274 $ 1,243
 

MOLYBDENUM (millions of
recoverable pounds)

(FCX's net interest in %)
Henderson (100%) 3 3 N/A N/A
Climax (100%) 6 5 N/A N/A
North America copper mines (100%)a 8 8 N/A N/A
Cerro Verde (53.56%) 7   7   N/A N/A
Consolidated 24 23 24 25
Less noncontrolling interests 3   3   4   3  
Net 21   20   20   22  
 
Average realized price per pound $ 12.89 $ 9.58
 
 
a. Amounts are net of Morenci's undivided joint venture partners'
interests.
b. Amounts are net of Grasberg's joint venture partner's
interest, which varies in accordance with the terms of the joint
venture agreement.
c. Consolidated sales volumes exclude purchased copper of 90
million pounds in second-quarter 2018 and 62 million pounds in
second- quarter 2017.
 
 
FREEPORT-McMoRan INC.
SELECTED OPERATING DATA (continued)
     
Six Months Ended June 30,
2018 2017 2018 2017
MINING OPERATIONS: Production Sales
Copper (millions of recoverable pounds)
(FCX's net interest in %)

North America

Morenci (72%)a 351 368 370 368
Bagdad (100%) 97 83 99 81
Safford (100%) 62 79 68 85
Sierrita (100%) 77 81 82 80
Miami (100%) 8 10 9 10
Chino (100%) 80 120 88 123
Tyrone (100%) 26 34 28 35
Other (100%) 1   1   1   1  
Total North America 702   776   745   783  
 

South America

Cerro Verde (53.56%) 505 522 500 512
El Abra (51%) 101   82   102   84  
Total South America 606   604   602   596  
 

Indonesia

Grasberg (90.64%)b 658   354   635   372  
Total 1,966 1,734 1,982 c 1,751 c
Less noncontrolling interests 346   316   342   314  
Net 1,620   1,418   1,640   1,437  
 
Average realized price per pound $ 3.10 $ 2.65
 
Gold (thousands of recoverable ounces)
(FCX's net interest in %)
North America (100%) 10 12 12 10
Indonesia (90.64%)b 1,335   580   1,274   604  
Consolidated 1,345 592 1,286 614
Less noncontrolling interests 125     54     120     57  
Net 1,220   538   1,166   557  
 
Average realized price per ounce $ 1,291 $ 1,242
 
Molybdenum (millions of recoverable pounds)
(FCX's net interest in %)
Henderson (100%) 7 6 N/A N/A
Climax (100%) 11 10 N/A N/A
North America (100%)a 15 17 N/A N/A
Cerro Verde (53.56%) 13   13   N/A N/A
Consolidated 46 46 48 49
Less noncontrolling interests 6   6   7   6  
Net 40   40   41   43  
 
Average realized price per pound $ 12.42 $ 9.16
 
 
a. Amounts are net of Morenci's undivided joint venture partners'
interests.
b. Amounts are net of Grasberg's joint venture partner's
interest, which varies in accordance with the terms of the joint
venture agreement.
c. Consolidated sales volumes exclude purchased copper of 164
million pounds for the first six months of 2018 and 120 million
pounds for the first six months of 2017.
 
 
FREEPORT-McMoRan INC.
SELECTED OPERATING DATA (continued)
       
Three Months Ended June 30, Six Months Ended June 30,
2018 2017 2018 2017
100% North America Copper Mines

Solution Extraction/Electrowinning
(SX/EW) Operations

Leach ore placed in stockpiles (metric tons per day) 689,500 692,700 682,100 697,300
Average copper ore grade (percent) 0.24 0.29 0.26 0.28
Copper production (millions of recoverable pounds) 268 282 530 559
 

Mill Operations

Ore milled (metric tons per day) 307,000 299,100 297,900 301,400
Average ore grades (percent):
Copper 0.35 0.39 0.35 0.40
Molybdenum 0.02 0.03 0.02 0.03
Copper recovery rate (percent) 89.1 86.7 88.5 86.6
Production (millions of recoverable pounds):
Copper 157 174 308 360
Molybdenum 9 9 16 18
 
100% South America Mining

SX/EW Operations

Leach ore placed in stockpiles (metric tons per day) 246,700 126,000 207,600 123,100
Average copper ore grade (percent) 0.30 0.36 0.32 0.39
Copper production (millions of recoverable pounds) 75 59 142 125
 

Mill Operations

Ore milled (metric tons per day) 385,200 347,600 385,300 343,300
Average ore grades (percent):
Copper 0.38 0.44 0.39 0.44
Molybdenum 0.01 0.02 0.01 0.02
Copper recovery rate (percent) 84.4 83.0 81.7 83.8
Production (millions of recoverable pounds):
Copper 238 241 464 479
Molybdenum 7 7 13 13
 
100% Indonesia Mining
Ore milled (metric tons per day):a
Grasberg open pit 148,400 88,600 136,800 71,200
Deep Ore Zone underground mine 29,200 27,300 34,300 26,800
Deep Mill Level Zone (DMLZ) underground mineb 2,700 3,800 2,700 3,500
Grasberg Block Cave underground mineb 3,800 3,800 3,900 3,200
Big Gossan underground mineb 3,800     3,100   800
Total 187,900   123,500   180,800   105,500
Average ore grades:
Copper (percent) 1.06 1.03 1.09 1.08
Gold (grams per metric ton) 1.77 1.16 1.71 1.17
Recovery rates (percent):
Copper 92.7 91.8 92.4 92.0
Gold 86.1 85.3 85.5 85.1
Production (recoverable):
Copper (millions of pounds) 353 221 693 393
Gold (thousands of ounces) 816 347 1,489 588
 
100% Molybdenum Mines
Ore milled (metric tons per day) 28,900 22,000 26,000 21,800
Average molybdenum ore grade (percent) 0.18 0.20 0.19 0.21
Molybdenum production (millions of recoverable pounds) 9 8 18 16
 
 
a. Amounts represent the approximate average daily throughput
processed at PT Freeport Indonesia's (PT-FI) mill facilities from
each producing mine and from development activities that result in
metal production.
b. Targeted production rates once the DMLZ underground mine
reaches full capacity are expected to approximate 80,000 metric tons
of ore per day in 2022; production from the Grasberg Block Cave
underground mine is expected to commence in the first half of 2019,
and production from the Big Gossan underground mine restarted in
fourth-quarter 2017.
 
 
FREEPORT-McMoRan INC.
CONSOLIDATED STATEMENTS OF INCOME (Unaudited)
     
Three Months Ended Six Months Ended
June 30, June 30,
2018 2017a 2018 2017a
(In Millions, Except Per Share Amounts)
Revenuesb $ 5,168 $ 3,711 $ 10,036 $ 7,052
Cost of sales:
Production and deliveryc 2,915 2,480 5,723 4,668
Depreciation, depletion and amortization 442   450   893   839  
Total cost of sales 3,357 2,930 6,616 5,507
Selling, general and administrative expensesc 109 107 240 258
Mining exploration and research expenses 24 19 45 33
Environmental obligations and shutdown costs 59 (21 ) 68 4
Net gain on sales of assets (45 ) (10 ) (56 ) (33 )
Total costs and expenses 3,504   3,025   6,913   5,769  
Operating income 1,664 686 3,123 1,283
Interest expense, netc,d (142 ) (162 ) (293 ) (329 )
Net gain (loss) on early extinguishment of debt 9 (4 ) 8 (3 )
Other income (expense), netc 20   (7 ) 49   e  
Income from continuing operations before income taxes and equity in
affiliated companies' net earnings (losses)
1,551 513 2,887 951
Provision for income taxesf (515 ) (186 ) (1,021 ) (360 )
Equity in affiliated companies' net earnings (losses) 3   (1 ) 1   3  
Net income from continuing operations 1,039 326 1,867 594
Net (loss) income from discontinued operationsg (4 ) 9   (15 ) 47  
Net income 1,035 335 1,852 641
Net income attributable to noncontrolling interests:
Continuing operations (166 ) (66 ) (291 ) (141 )
Discontinued operations   (1 )   (4 )
Net income attributable to FCX common stockh $ 869   $ 268   $ 1,561   $ 496  
 
Basic net income (loss) per share attributable to common stock:
Continuing operations $ 0.60 $ 0.18 $ 1.08 $ 0.31
Discontinued operations     (0.01 ) 0.03  
$ 0.60   $ 0.18   $ 1.07   $ 0.34  
 
Diluted net income (loss) per share attributable to common stock:
Continuing operations $ 0.59 $ 0.18 $ 1.08 $ 0.31
Discontinued operations     (0.01 ) 0.03  
$ 0.59   $ 0.18   $ 1.07   $ 0.34  
 
Weighted-average common shares outstanding:
Basic 1,449   1,447   1,449   1,447  
Diluted 1,458   1,453   1,458   1,453  
 
Dividends declared per share of common stock $ 0.05   $   $ 0.10   $  
 

a.

 

The adoption of accounting guidance related to the presentation
of retirement benefits resulted in the reclassification of the
non-service components of net periodic benefit cost to other
income (expense), net.

b.

Revenues include adjustments to provisionally priced
concentrate and cathode sales. For a summary of adjustments to
provisionally priced copper sales, refer to the supplemental
schedule, "Derivative Instruments," beginning on page VIII.

c.

Includes net mining and oil and gas charges that are summarized
in the supplemental schedule, "Adjusted Net Income," on page VII.

d.

Consolidated interest costs (before capitalization) totaled
$165 million in second-quarter 2018, $192 million in
second-quarter 2017, $341 million for the first six months of 2018
and $387 million for the first six months of 2017.

e.

Includes interest received by PT-FI with the refund of prior
years' tax receivables, which is summarized in the supplemental
schedule, "Adjusted Net Income," on page VII.

f.

For a summary of FCX's provision for income taxes, refer to the
supplemental schedule, "Income Taxes," on page VIII.

g.

Primarily reflects adjustments to the estimated fair value of
contingent consideration related to the 2016 sale of FCX's
interest in TF Holdings Limited (TFHL), which will continue to be
adjusted through December 31, 2019.

h.

FCX defers recognizing profits on intercompany sales until
final sales to third parties occur. Refer to the supplemental
schedule, "Deferred Profits," on page IX for a summary of net
impacts from changes in these deferrals.

 
 
FREEPORT-McMoRan INC.
CONSOLIDATED BALANCE SHEETS (Unaudited)
   
June 30, December 31,
2018 2017
(In Millions)
ASSETS
Current assets:
Cash and cash equivalents $ 3,859 $ 4,447
Trade accounts receivable 1,077 1,246
Income and other tax receivables 225 325
Inventories:
Mill and leach stockpiles 1,435 1,422
Materials and supplies, net 1,404 1,305
Product 1,337 1,166
Other current assets 381 270
Held for sale 625   508  
Total current assets 10,343 10,689
Property, plant, equipment and mine development costs, net 22,923 22,934
Long-term mill and leach stockpiles 1,371 1,409
Other assets 2,391   2,270  
Total assets $ 37,028   $ 37,302  
 
LIABILITIES AND EQUITY
Current liabilities:
Accounts payable and accrued liabilities $ 2,420 $ 2,321
Accrued income taxes 569 565
Current portion of environmental and asset retirement obligations 380 388
Dividends payable 73
Current portion of debt 4 1,414
Held for sale 353   323  
Total current liabilities 3,799 5,011
Long-term debt, less current portion 11,123 11,703
Deferred income taxes 3,702 3,649
Environmental and asset retirement obligations, less current portion 3,631 3,631
Other liabilities 1,931   2,012  
Total liabilities 24,186 26,006
 
Equity:
Stockholders' equity:
Common stock 158 158
Capital in excess of par value 26,667 26,751
Accumulated deficit (13,161 ) (14,722 )
Accumulated other comprehensive loss (464 ) (487 )
Common stock held in treasury (3,726 ) (3,723 )
Total stockholders' equity 9,474 7,977
Noncontrolling interests 3,368   3,319  
Total equity 12,842   11,296  
Total liabilities and equity $ 37,028   $ 37,302  
 
 
FREEPORT-McMoRan INC.
CONSOLIDATED STATEMENTS OF CASH FLOWS (Unaudited)
 
 
Six Months Ended June 30,
2018   2017
(In Millions)
Cash flow from operating activities:
Net income $ 1,852 $ 641
Adjustments to reconcile net income to net cash provided by
operating activities:
Depreciation, depletion and amortization 893 839
Net gain on sales of assets (56 ) (33 )
Stock-based compensation 60 44
Payments for Cerro Verde royalty dispute (21 ) (21 )
Net charges for environmental and asset retirement obligations,
including accretion
152 87
Payments for environmental and asset retirement obligations (110 ) (59 )
Net charges for defined pension and postretirement plans 38 70
Pension plan contributions (44 ) (56 )
Net (gain) loss on early extinguishment of debt (8 ) 3
Deferred income taxes 61 55
Loss (gain) on disposal of discontinued operations 15 (38 )
Decrease in long-term mill and leach stockpiles 38 80
Non-cash drillship settlements/idle rig costs and other oil and gas
adjustments
(33 )
Oil and gas contract settlement payments (70 )
Other, net 21 (23 )
Changes in working capital and other tax payments:
Accounts receivable 309 589
Inventories (468 ) (101 )
Other current assets (20 ) (2 )
Accounts payable and accrued liabilities 114 (267 )
Accrued income taxes and timing of other tax payments (148 ) 124  
Net cash provided by operating activities 2,678   1,829  
 
Cash flow from investing activities:
Capital expenditures:
North America copper mines (232 ) (67 )
South America (138 ) (45 )
Indonesia (449 ) (457 )
Molybdenum mines (2 ) (2 )
Other (63 ) (135 )
Intangible water rights and other, net (86 ) 3  
Net cash used in investing activities (970 ) (703 )
 
Cash flow from financing activities:
Proceeds from debt 352 606
Repayments of debt (2,297 ) (1,250 )
Cash dividends paid:
Common stock (73 ) (2 )
Noncontrolling interests (241 ) (39 )
Stock-based awards net proceeds (payments) 5 (8 )
Debt financing costs and other, net (23 ) (11 )
Net cash used in financing activities (2,277 ) (704 )
 
Net (decrease) increase in cash, cash equivalents, restricted cash
and restricted cash equivalents
(569 ) 422
Decrease in cash and cash equivalents in assets held for sale 44 7
Cash, cash equivalents, restricted cash and restricted cash
equivalents at

beginning of year

4,631   4,403  
Cash, cash equivalents, restricted cash and restricted cash
equivalents at

end of perioda

$ 4,106   $ 4,832  
 

a. Includes restricted cash and restricted cash
equivalents of $247 million at June 30, 2018, and $165 million at
June 30, 2017.

 

FREEPORT-McMoRan INC.
ADJUSTED NET INCOME

Adjusted net income is intended to provide investors and others with
information about FCX's recurring operating performance. This
information differs from net income attributable to common stock
determined in accordance with U.S. generally accepted accounting
principles (GAAP) and should not be considered in isolation or as a
substitute for measures of performance determined in accordance with
U.S. GAAP. FCX's adjusted net income follows, which may not be
comparable to similarly titled measures reported by other companies (in
millions, except per share amounts).

 
Three Months Ended June 30,
2018 2017
Pre-tax After-taxa   Per Share Pre-tax After-taxa   Per Share
Net income attributable to common stock N/A $ 869   $ 0.59   N/A $ 268   $ 0.18  
 
PT-FI net charges for workforce reductions (87 ) b (46 ) (0.03 )
Other net mining credits (charges) 14 c 9 0.01 (9 ) (9 ) (0.01 )
Net oil and gas credits 6 6
Net adjustments to environmental obligations and related litigation
reserves
(50 ) (50 ) (0.03 ) 30 30 0.02
Net gain on sales of assets 45 d 45 0.03 10 10 0.01
Net gain (loss) on early extinguishment of debt 9 9 0.01 (4 ) (4 )
Net tax creditse N/A 7 N/A 32 0.02
(Loss) gain on discontinued operationsf (4 ) (4 )   10   8    
$ 14   $ 16   $ 0.01   g $ (44 ) $ 27   $ 0.01  
 
Adjusted net income attributable to common stock N/A $ 853 $ 0.58 N/A $ 241 $ 0.17
 
Six Months Ended June 30,
2018 2017
Pre-tax After-taxa Per Share Pre-tax After-taxa Per Share
Net income attributable to common stock N/A $ 1,561   $ 1.07   N/A $ 496   $ 0.34  
 
PT-FI charges for workforce reductions $ $ $ $ (108 ) b $ (57 ) $ (0.04 )
Other net mining credits (charges) 10 c 8 0.01 (28 ) (28 ) (0.02 )
Net oil and gas credits 4 h 4 0.01
Net adjustments to environmental obligations and related litigation
reserves
(50 ) (50 ) (0.03 ) 11 11 0.01
Net gain on sales of assets 56 d 56 0.04 33 33 0.02
Net gain (loss) on early extinguishment of debt 8 8 (3 ) (3 )
PT-FI interest on tax refund 24 i 13 0.01
Net tax creditse N/A 7 N/A 31 0.02
(Loss) gain on discontinued operationsf (15 ) (15 ) (0.01 ) 51   43   0.03  
$ 33   $ 27   $ 0.02   $ (40 ) $ 34   $ 0.02   g
 
Adjusted net income attributable to common stock N/A $ 1,534 $ 1.05 N/A $ 462 $ 0.32
 

a.

 

Reflects impact to FCX net income attributable to common stock
(i.e., net of any taxes and noncontrolling interests).

b.

Includes charges totaling $82 million in second-quarter 2017
and $103 million for the first six months of 2017 in production
and delivery costs and $5 million for the second quarter and first
six months of 2017 in selling, general and administrative expenses.

c.

Includes net credits totaling $10 million for the second
quarter and first six months of 2018 in production and delivery
costs and $6 million for the second quarter and first six months
of 2018 in other income (expense), net, partly offset by interest
expense totaling $2 million in second-quarter 2018 and $6 million
for the first six months of 2018.

d.

Reflects adjustments to the estimated fair value of the
potential $150 million in contingent consideration related to the
2016 sale of onshore California oil and gas properties, which will
continue to be adjusted through December 31, 2020.

e.

Refer to "Income Taxes" on page VIII, for further discussion of
net tax credits.

f.

Primarily reflects adjustments to the estimated fair value of
the potential $120 million in contingent consideration related to
the 2016 sale of FCX's interest in TFHL, which will continue to be
adjusted through December 31, 2019.

g.

Does not foot because of rounding.

h.

Includes adjustments to the fair value of contingent payments
totaling $26 million in production and delivery costs related to
the 2016 drillship settlements, partly offset by charges totaling
$22 million in selling, general and administrative expenses
primarily for contract termination costs.

i.

Reflects interest received with the refund of prior years' tax
receivables.

 

View Comments and Join the Discussion!