Omega Morgan Will Move Portland's Sellwood Bridge January 19

Loading...
Loading...

Bridge will be moved in one piece; called one of longest bridge moves attempted

Portland, Oregon (PRWEB) January 02, 2013

CONTACT: Olga Haley for Omega Morgan
olga@leoketel.com; 503-860-0848

The Sellwood Bridge, with a truss span 1,100 feet long, 75 feet high and 28 feet wide, crosses the Willamette River and links SW Portland to its SE business district and suburbs. On January 19, Omega Morgan (http://www.omegamorgan.com) will undertake one of the longest bridge moves ever when it shifts the Sellwood Bridge in one piece and on a radius to the north.

The old Sellwood Bridge will then become a temporary route for the 30,500 vehicles that cross it each day, while work begins on the new $307.5 million bridge, due to be completed in 2016.

“We are really pleased to be involved in this important, complex and exciting project said John McCalla, CEO/president of Omega Morgan, one of the West Coast's leading moving, rigging and transportation companies.

Both Omega Morgan and general contractors Slayden/Sundt Joint Venture have successfully used this detour bridge method for other projects. “Omega Morgan has moved bridges weighing upwards of eight million pounds, but this one does offer some additional challenges,” McCalla said.

The company's chief engineer, Ralph DiCaprio, said the company welcomes the challenges. This is why we like what we do. There's something different on every project,” he said.

Devising a strategy to move the bridge in one piece helped Omega Morgan win the contract after showing that it would save time, money and duplication of efforts, according to parties involved in the project. Other proposals had suggested expensive and redundant structural features and extensive staging.

The plan is to use hydraulic jacks to lift the bridge onto skid gear and then to move and mount it on new piers that have been built in the river. The aging bridge will then become the “shoofly” or detour while construction begins on the new bridge. Officials on the project said the temporary bridge will be inspected before it is open to traffic.

The 87-year-old bridge replaced a ferry called the John F. Caples, a steam-powered vessel that took 582 vehicles and 452 pedestrians across the Willamette River each day. It was Portland's first fixed-span bridge, meaning that it did not have a draw or swing span.

The decision was made to replace the Sellwood Bridge because it cannot handle the current volume of traffic, has a low rating on a federal bridge rating, and buses and heavy trucks are restricted from using the bridge. It also has narrow lanes and sidewalk, no bike facilities and it is not designed to withstand earthquakes even though the area is in one of the most dangerous earthquake zones in the U.S.

Omega Morgan provides innovative solutions for the complex lifting, moving, rigging and transportation challenges faced by manufacturers, power generation companies, general contractors and logistics providers. For more information call Omega Morgan in Portland at
503-647-7474 or 800-442-8141; Seattle at 253-852-7500; Phoenix at 602-789-4143 or
visit http://www.omegamorgan.com.

For the original version on PRWeb visit: http://www.prweb.com/releases/prweb2013/1/prweb10281291.htm

Loading...
Loading...
Market News and Data brought to you by Benzinga APIs
Benzinga simplifies the market for smarter investing

Trade confidently with insights and alerts from analyst ratings, free reports and breaking news that affects the stocks you care about.

Join Now: Free!

Loading...