Taseko Commences Commissioning of GDP3 Concentrator

Loading...
Loading...

VANCOUVER, Dec. 17, 2012 /PRNewswire/ - Taseko TKO (the "Company") is pleased to announce that the commissioning phase of the $325 million Gibraltar Development Project 3 (GDP 3) has begun.

The electrical power distribution and reclaim water systems have been successfully tied in and are now operational and water testing of the new tailings system is underway.

Commissioning will continue into January and it is expected that first ore will be delivered to the new concentrator immediately thereafter, with commercial production targeted by the end of March.

Russell Hallbauer, President and CEO of Taseko, commented, "In the twenty months since awarding the construction management contract, we have successfully built a new 30,000 ton per day concentrator and associated infrastructure, on time and on budget for $235 million.  This new concentrator, along with the $90 million of new state-of-the-art mining equipment, will increase Gibraltar's production capabilities to 85,000 tons per day by mid-2013. Gibraltar will have two distinct production trains which will significantly enhance our operational flexibility. As metal production increases over the course of the year while we ramp up our daily mill throughput, operating costs will decline from those experienced over the latter part of 2012."

Russell Hallbauer
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

CAUTION REGARDING FORWARD-LOOKING INFORMATION

This document contains "forward-looking statements" that were based on Taseko's expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should" and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties and costs related to the Company's exploration and development activities, such as those associated with continuity of mineralization or determining whether mineral resources or reserves exist on a property;
  • uncertainties related to the accuracy of our estimates of mineral reserves, mineral resources, production rates and timing of production, future production and future cash and total costs of production and milling;
  • uncertainties related to feasibility studies that provide estimates of expected or anticipated costs, expenditures and economic returns from a mining project;
  • uncertainties related to our ability to complete the mill upgrade on time estimated and at the scheduled cost;
  • uncertainties related to the ability to obtain necessary licenses permits for development projects and project delays due to third party opposition;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations, particularly laws, regulations and policies;
  • changes in general economic conditions, the financial markets and in the demand and market price for copper, gold and other minerals and commodities, such as diesel fuel, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • the effects of forward selling instruments to protect against fluctuations in copper prices and exchange rate movements and the risks of counterparty defaults, and mark to market risk;
  • the risk of inadequate insurance or inability to obtain insurance to cover mining risks;
  • the risk of loss of key employees; the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates;
  • environmental issues and liabilities associated with mining including processing and stock piling ore; and
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate mines, or environmental hazards, industrial accidents or other events or occurrences, including third party interference that interrupt the production of minerals in our mines.

For further information on Taseko, investors should review the Company's annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com

SOURCE Taseko Mines Limited

Loading...
Loading...
Market News and Data brought to you by Benzinga APIs
Posted In: Press Releases
Benzinga simplifies the market for smarter investing

Trade confidently with insights and alerts from analyst ratings, free reports and breaking news that affects the stocks you care about.

Join Now: Free!

Loading...